Power outages in Woluwe-Saint-Lambert

Low voltage

Solved streets

avenue Robert Dalechamp, avenue de Juillet
Solved in
4 hours 1 minute
Duration
From 11 June 2022 11h49
until 11 June 2022 15h50
Sibelga ensures that information about power cuts is communicated as quickly as possible. This communication is always subject to change and may be adjusted by Sibelga if necessary.

outage_updates.title

19h40

Outage solved

he power outage is solved
14h50

Repair time extended

Unfortunately we need more time to solve the outage. Probable new end time is 15h50.
13h43

Repair time extended

Unfortunately we need more time to solve the outage. Probable new end time is 15h00.
11h50

Power outage identified

Outage discovered by Sibelga at 11h49
Probable end time: 13h19.