Power outages in Anderlecht

High voltage

Solved streets

rue de la Bienvenue, rue Bollinckx
Solved in
1 hour 52 minutes
Duration
From 14 June 2025 22h04
until 14 June 2025 23h57
Sibelga ensures that information about power cuts is communicated as quickly as possible. This communication is always subject to change and may be adjusted by Sibelga if necessary.

outage_updates.title

23h57

Outage solved

he power outage is solved
23h42

Repair time extended

Unfortunately we need more time to solve the outage. Probable new end time is 01h00.
23h41

Outage solved in following streets:

80% of the customers have power again
rue de la Bienvenue, rue Bollinckx
22h16

Outage solved in following streets:

50% of the customers have power again
rue de la Bienvenue, rue Bollinckx
22h08

Power outage identified

Outage discovered by Sibelga at 22h04
Probable end time: 23h34.