27 mar 2020

Bruxelles (Laeken)

Back to all outages
Solved
Solved in 9 hours and 50 minutes
From 1:05 to 10:56

Resolved streets *

allée des Moutons, avenue Huldergem, avenue Jean de Bologne, avenue Mutsaard, avenue Wannecouter, avenue de Busleyden, avenue de l'Amphore, avenue de la Brise, avenue de la Bugrane, avenue de la Nivéole, avenue des Liserons, avenue des Pagodes, avenue du Forum, chaussée Romaine, rue De Wand, rue Gustave Demanet, rue Paul Janson

Updates

10:56
 

Outage solved

The power outage is solved

3:11
 

Extended repair time

The complete repair takes longer than expected.
New estimated repair time: 2:49

2:51
 

Outage solved in the following streets *

99% of customers have power
avenue Jean de Bologne, avenue de Busleyden, avenue de l'Amphore, avenue du Forum

2:41
 

Extended repair time

The complete repair takes longer than expected.
New estimated repair time: 3:35

2:39
 

Outage solved in the following streets *

51% of customers have power
avenue de la Brise, avenue des Pagodes

1:24
 

Outage solved in the following streets *

45% of customers have power
allée des Moutons, avenue Huldergem, avenue Mutsaard, avenue Wannecouter, avenue de la Bugrane, avenue de la Nivéole, avenue des Liserons, chaussée Romaine, rue De Wand, rue Gustave Demanet, rue Paul Janson

1:05
 

Power outage identified

Outage discovered by Sibelga at 1:05, expected end date 2:35