Power cuts

14 oct 2021

Bruxelles

Back to all outages
Solved
Solved in 6 hours and 19 minutes
From 9:25 to 15:44

Resolved streets *

avenue de Cortenbergh, rue Franklin, rue Le Corrège, rue Le Tintoret, rue Le Titien, rue Rembrandt, rue Véronèse

Updates

15:44
 

Outage solved

The power outage is solved

13:55
 

Extended repair time

The complete repair takes longer than expected.
New estimated repair time: 16:00

13:03
 

Extended repair time

The complete repair takes longer than expected.
New estimated repair time: 14:00

10:50
 

Outage solved in the following streets *

100% of customers have power
avenue de Cortenbergh, rue Franklin, rue Le Corrège, rue Le Tintoret, rue Le Titien, rue Rembrandt, rue Véronèse

10:49
 

Extended repair time

The complete repair takes longer than expected.
New estimated repair time: 12:00

9:25
 

Power outage identified

Outage discovered by Sibelga at 9:25, expected end date 10:55