Power outages in Forest, Anderlecht

High voltage

Solved streets

rue Bollinckx, boulevard de l'Humanité, rue de la Bienvenue, rue Bollinckx, boulevard Industriel
Solved in
3 hours 52 minutes
Duration
From 26 May 2026 02h12
until 26 May 2026 06h05
Sibelga ensures that information about power cuts is communicated as quickly as possible. This communication is always subject to change and may be adjusted by Sibelga if necessary.

outage_updates.title

06h05

Outage solved

he power outage is solved
05h25

Outage solved in following streets:

93% of the customers have power again
rue Bollinckx, boulevard de l'Humanité, rue de la Bienvenue, rue Bollinckx, boulevard Industriel
05h10

Repair time extended

Unfortunately we need more time to solve the outage. Probable new end time is 06h20.
04h12

Outage solved in following streets:

81% of the customers have power again
rue Bollinckx, boulevard de l'Humanité, rue de la Bienvenue, rue Bollinckx, boulevard Industriel
04h08

Repair time extended

Unfortunately we need more time to solve the outage. Probable new end time is 05h20.
03h21

Outage solved in following streets:

62% of the customers have power again
rue Bollinckx, boulevard de l'Humanité, boulevard Industriel
03h19

Outage solved in following streets:

55% of the customers have power again
rue Bollinckx, boulevard de l'Humanité, boulevard Industriel
02h15

Power outage identified

Outage discovered by Sibelga at 02h12
Probable end time: 03h42.