Power outages in Woluwe-Saint-Lambert

Low voltage

Solved streets

avenue Guillaume Abeloos, avenue Constant Montald, avenue A.J. Slegers
Solved in
1 hour 1 minute
Duration
From 20 April 2026 09h18
until 20 April 2026 10h20
Sibelga ensures that information about power cuts is communicated as quickly as possible. This communication is always subject to change and may be adjusted by Sibelga if necessary.

outage_updates.title

11h07

Outage solved

he power outage is solved
10h45

Repair time extended

Unfortunately we need more time to solve the outage. Probable new end time is 12h00.
09h28

Power outage identified

Outage discovered by Sibelga at 09h18
Probable end time: 10h48.