Power outages in Forest, Saint-Gilles

Low voltage

Solved streets

rue de Belgrade, rue de Belgrade
Solved in
2 hours 26 minutes
Duration
From 02 April 2026 18h03
until 02 April 2026 20h30
Sibelga ensures that information about power cuts is communicated as quickly as possible. This communication is always subject to change and may be adjusted by Sibelga if necessary.

outage_updates.title

21h27

Outage solved

he power outage is solved
20h30

Repair time extended

Unfortunately we need more time to solve the outage. Probable new end time is 21h29.
19h31

Repair time extended

Unfortunately we need more time to solve the outage. Probable new end time is 20h29.
18h07

Power outage identified

Outage discovered by Sibelga at 18h03
Probable end time: 19h33.