Power outages in Schaerbeek

Low voltage

Solved streets

rue Hubert Krains
Solved in
4 hours 24 minutes
Duration
From 01 June 2026 09h09
until 01 June 2026 13h33
Sibelga ensures that information about power cuts is communicated as quickly as possible. This communication is always subject to change and may be adjusted by Sibelga if necessary.

outage_updates.title

13h33

Outage solved

he power outage is solved
12h30

Repair time extended

Unfortunately we need more time to solve the outage. Probable new end time is 13h39.
11h35

Repair time extended

Unfortunately we need more time to solve the outage. Probable new end time is 11h39.
09h10

Power outage identified

Outage discovered by Sibelga at 09h09
Probable end time: 10h39.