Power outages in Woluwe-Saint-Lambert

Low voltage

Solved streets

avenue du Capricorne
Solved in
5 hours 41 minutes
Duration
From 27 April 2026 09h00
until 27 April 2026 14h42
Sibelga ensures that information about power cuts is communicated as quickly as possible. This communication is always subject to change and may be adjusted by Sibelga if necessary.

outage_updates.title

14h42

Outage solved

he power outage is solved
12h34

Repair time extended

Unfortunately we need more time to solve the outage. Probable new end time is 13h30.
11h39

Repair time extended

Unfortunately we need more time to solve the outage. Probable new end time is 12h30.
10h20

Repair time extended

Unfortunately we need more time to solve the outage. Probable new end time is 11h30.
09h39

Power outage identified

Outage discovered by Sibelga at 09h00
Probable end time: 10h30.