Power outages in Saint-Josse-ten-Noode

Low voltage

Solved streets

rue de l'Ascension, rue de la Poste, rue des Secours, rue Verte
Solved in
4 hours 12 minutes
Duration
From 20 February 2026 18h08
until 20 February 2026 22h20
Sibelga ensures that information about power cuts is communicated as quickly as possible. This communication is always subject to change and may be adjusted by Sibelga if necessary.

outage_updates.title

22h37

Outage solved

he power outage is solved
22h29

Repair time extended

Unfortunately we need more time to solve the outage. Probable new end time is 23h38.
21h40

Repair time extended

Unfortunately we need more time to solve the outage. Probable new end time is 22h38.
20h43

Repair time extended

Unfortunately we need more time to solve the outage. Probable new end time is 21h38.
19h02

Repair time extended

Unfortunately we need more time to solve the outage. Probable new end time is 20h38.
18h10

Power outage identified

Outage discovered by Sibelga at 18h08