Power outages in Jette

Low voltage

Solved streets

place Cardinal Mercier, avenue des Démineurs, rue Jules Lahaye, rue Saint-Vincent de Paul, rue Léon Théodor, avenue Charles Woeste
Solved in
3 hours 20 minutes
Duration
From 19h55 until 23h15
Sibelga ensures that information about power cuts is communicated as quickly as possible. This communication is always subject to change and may be adjusted by Sibelga if necessary.

outage_updates.title

23h47

Outage solved

he power outage is solved
23h23

Repair time extended

Unfortunately we need more time to solve the outage. Probable new end time is 23h59.
22h51

Repair time extended

Unfortunately we need more time to solve the outage. Probable new end time is 23h30.
22h00

Repair time extended

Unfortunately we need more time to solve the outage. Probable new end time is 23h00.
20h33

Repair time extended

Unfortunately we need more time to solve the outage. Probable new end time is 22h05.
19h58

Power outage identified

Outage discovered by Sibelga at 19h55
Probable end time: 22h00.