Power outages in Saint-Gilles

Low voltage

Solved streets

rue de la Croix de Pierre
Solved in
4 hours 51 minutes
Duration
From 23 April 2026 12h38
until 23 April 2026 17h30
Sibelga ensures that information about power cuts is communicated as quickly as possible. This communication is always subject to change and may be adjusted by Sibelga if necessary.

outage_updates.title

22h50

Outage solved

he power outage is solved
17h40

Repair time extended

Unfortunately we need more time to solve the outage. Probable new end time is 18h45.
14h36

Repair time extended

Unfortunately we need more time to solve the outage. Probable new end time is 16h00.
12h43

Power outage identified

Outage discovered by Sibelga at 12h38
Probable end time: 14h08.