Power outages in Jette

Low voltage

Solved streets

rue Vanderborght
Solved in
2 hours 19 minutes
Duration
From 18 March 2026 12h10
until 18 March 2026 14h30
Sibelga ensures that information about power cuts is communicated as quickly as possible. This communication is always subject to change and may be adjusted by Sibelga if necessary.

outage_updates.title

15h23

Outage solved

he power outage is solved
14h48

Repair time extended

Unfortunately we need more time to solve the outage. Probable new end time is 16h00.
13h33

Repair time extended

Unfortunately we need more time to solve the outage. Probable new end time is 14h40.
12h15

Power outage identified

Outage discovered by Sibelga at 12h10
Probable end time: 13h40.