Power outages in Schaerbeek

Low voltage

Solved streets

rue Renkin
Solved in
5 hours 7 minutes
Duration
From 25 July 2025 03h23
until 25 July 2025 08h30
Sibelga ensures that information about power cuts is communicated as quickly as possible. This communication is always subject to change and may be adjusted by Sibelga if necessary.

outage_updates.title

10h34

Outage solved

he power outage is solved
09h42

Repair time extended

Unfortunately we need more time to solve the outage. Probable new end time is 11h00.
09h05

Repair time extended

Unfortunately we need more time to solve the outage. Probable new end time is 10h00.
07h37

Repair time extended

Unfortunately we need more time to solve the outage. Probable new end time is 09h00.
05h29

Repair time extended

Unfortunately we need more time to solve the outage. Probable new end time is 07h30.
03h26

Power outage identified

Outage discovered by Sibelga at 03h23
Probable end time: 04h53.