Road work in Etterbeek, Bruxelles
Download the detailed plan (Osiris pdf)
Purpose of works
Electricity cables
Replacing low-voltage and/or high-voltage cables and installations.
Fibre network
Installation of a fibre optic network for the construction of our intelligent network, but also on behalf of other public services or institutions.
Voltage change
Replacing the 230-volt network with a 400-volt network.
Timeline
road_work_timeline.title
Phase 1: Av. de la Joyeuse Entrée
- Authorised duration: 19 jours ouvrables
- Execution period: between 6/04/2023 - 5/05/2023
- Concerned streets:
Av. de la Joyeuse Entrée (between Petite rue de la Loi and Av. de Cortenbergh)
Petite rue de la Loi
- Type of works: Renovation of electricity network, fibre optics
- Points of attention:
L'avenue de la Joyeuse Entrée will be completely closed to traffic
Diversions via rue Archimède/Franklin/Corrège
Access totunnel Joyeuse entrée will be maintained
Phase 2: Schuman Square / Av. de Cortenberg
- Authorised duration: 8 working days
- Execution period : Between 8/05/2023 - 14/05/2023
- Affected streets:
Schuman Square
Avenue Cortenbergh
- Type of works: Renovation of electricity network, fibre optics
- Points of attention:
Schuman Square: 2 lanes instead of 3
Av. de Cortenbergh: 1 lane instead of 3
Phase 3: Shuman Square / Rue Froissart
- Authorised duration: 6 working days
- Execution period : Between 18/05/2023 - 25/05/2023
- Streets affected:
Schuman Square (between Rue Froissart and Avenue d'Auderghem)
Rue Froissart (between 133 and 143)
- Type of works: Renovation of electricity network, fibre optics
- Points of attention:
Rue Froissart and Avenue d'Auderghem will temporarily become one-way streets
Phase 4: Rue Breydel / Av. d'Auderghem
- Authorised duration: 24 working days
- Execution period : Between 26/05/2023 - 28/06/2023
- Affected streets:
Rue Breydel
Avenue d'Auderghem
- Type of works: Renovation of electricity network, fibre optics
- Points of attention:
Avenue d'Auderghem becomes one-way street
Phase 5: Joyeuse Entrée / Loi / Schuman / Av. d'Auderghem
- Authorised duration: 22 working days
- Period: between 29/06/2023 and 4/08/2023
- Affected streets :
Avenue de la Joyeuse Entrée (from 1 to 21)
Petite rue de la Loi (from 219 to 235)
Schuman (between Rue de Loi and Avenue d'Auderghem)
Avenue d'Auderghem (from 2 to 26)
- Work to be carried out: Renovation of the electricity network, fibre optics
- Points of attention :
Avenue d'Auderghem will become a one-way street
From 17/7 to 21/7, no work due to the European summit and the National Day
Phase 6: Schuman / Av. de Cortenbergh
- Authorised duration:22 working days
- Period : Between 7/08/2023 - 28/08/2023
- Affected streets:
Schuman Square
Avenue Cortenbergh
- Tyoe of works: Renovation of electricity network, fibre optics
- Points of attention:
Schuman Square: 2 lanes instead of 3
Phase 7: rue de la Loi
- Authorised duration: 5 working days
- Period : Between 7/07/2023 - 28/08/2023 (*)
- Affected streets :
rue de la Loi (from 85 to 145-Lex Building)
- Type of works: Renovation of electricity network, fibre optics
- Point of attention:
Abolition of one lane for smooth traffic pedestrians and cyclists
(*) these dates may be postponed to a later period.
Phase 8: rue de la Loi
- Authorised duration: 16 working days
- Period : Between 22/08/2023 - 12/09/2023 (*)
- Affected streets:
rue de la Loi(from 76 to Maelbeek valley garden)
- Type of works: Renovation of electricity network, fibre optics
- Concerns:
Abolition of one lane for smooth traffic pedestrians and cyclists
Only 1accessible lane on chaussée d'Etterbeek during the works
(*) these dates may be postponed to a later period